Hi All,

 

I have a question regarding demand load into MRS. Lets see i have 2 work orders with the following data:

 

Work Order 1:

Main Work center : Shop A

Op Work Center : Mechanic

 

Work Order 2:

Main Work Center: Shop A

Op Work Center: Electric

 

 

Is it possible to select in MRS Shop A as the planning node but getting into MRS the demands generated for the sub-nodes, in this case Mechanic and Electric?

 

Another question I have is regarding capacity availability:

 

Let's say that i have a work center hierarchy in SAP PM  (CR21) for my Mechanic crew that will have total availability of 30hr/day taking into consideration the work centers used for that hierarchy.

 

Level 0 Mechanic 30 hrs/day

     Level 1 Mechanic A 10 hrs/day

     Level 1 Mechanic B  20 hrs/ day

 

Is it possible to see this 30 hrs/day availability in MRS when using the main level to search for my demands?

 