Planned Order Planned Opening Date Calculation

$
0
0

Hi Experts,

 

I have come across with a situation that how Planned Opening Date calculation happening in Planned order if Inhouse production time is not maintained.

 

 

As I have faced a situation where I have not maintained the In-house production time in Material Master, If I am giving the order finish date as 21/12/2015, then system is automatically calculating the planned opening date as 21/11/2015(around 30 days minus).


Let me know from where this 30 days are picking for calculating the planned opening time.

 

I have checked OPPQ, nowhere I hv seen this 30 days.. and MRP group is not maintained for this material.

 

 

Thanks,

Aravind S