On his previous answer, Rupesh referred to a note which clearly explains that MRP will create a single replenishment proposal for requirements on the same date. This is standard and the system behavior cannot be changed in customizing.
A workaround using a BAdI is described on the following document:
How to create separate planned order / purchase requesition for same date
BR
Caetano